Details No of Project Total  Allocation  Total Expenditure  Bills in Hand  for Balance Allocation  Bills in Hand  without  Allocation Physical Progress
Fully Completed
Gampereliya  338           27,513,872.33                 27,513,872.33                           -                                   -   338
Sapiri Gamak  Rural Development  Programme 2020 88      84,460,237.82          84,241,075.28     219,162.54    10,199,233.31 88
RIDP 2020 18        4,885,735.18            4,836,987.37                   -                          -   18
Housing  480    122,013,591.23        122,013,499.00                   -                          -   480
Sanitation Programme 200             15,000.00                 15,000.00                   -     200
Water Supply Programme 201        9,964,713.72            9,964,713.72                   -     201
Pre School Building at Sivapuram 1           317,933.33               317,933.33                   -     1
Domestic Electricity Connection 165        3,300,000.00            3,300,000.00                   -     165
DCB 111        4,232,410.60            4,232,410.60                   -     111
Resettlement Assistance for Refugee Returnees from India 37        1,221,000.00            1,221,000.00           693,000.00 37
Pre School Building Earth filling at Sivapuram 1           743,216.15               743,216.15                   -     1
Construction of Smart Classroom 2           874,566.00               874,566.00                   -     2
Task force on Resettlement of Protracted  IDPP's 179      24,078,867.68          24,077,300.20      45,977,375.42 179
Pakistan, Bahrin Housing total 460                                -        41,691,000.00 460
Economic Empowerment of Women through Apparel based Mini Factories 1                                -             727,693.33 1
Gramasakkthi             12                                -          5,610,402.50 12
Establishment of school computer lab  1           226,474.45               226,474.45                   -     1
ONUR  1        3,991,237.36            3,991,237.36                   -                          -   1
Development Asst. Programme 19        8,607,420.00            8,607,420.00                   -     19
Resettlement Activities  for 2020 2        4,000,000.00            3,991,875.12     2
Thiyavarapiyasa Repair Housing  7           700,000.00               100,000.00     600,000.00   7
Rehabilitation & Improvement work 5           576,300.00               576,123.11                   -     5
Milatun Nabi   works (2018) 1                                -             343,000.00 1
Total 2330    301,722,575.85        300,844,704.02     819,162.54  105,241,704.56 2330
Scroll To Top